Construction Draw Schedule in Ontario: How Construction Loans Actually Fund in 2026
The foundation is poured, the framer wants paying on Friday, and the lender has just told your client the next draw is on hold. Not declined, just held: the quantity surveyor's report shows the remaining budget does not cover the cost to finish, and a lien search turned up something the lawyer wants explained. This is where most construction files in Ontario get stuck, and it is rarely about the approval itself. A construction loan is not one advance. It is a series of small closings, each with its own inspection, cost check, title search and holdback calculation. Knowing how the construction draw schedule in Ontario works, and what the lender's cost consultant and lawyer test before every advance, is the difference between a build that funds on time and one that stalls with trades on site. This guide is written for Ontario mortgage brokers and agents and for the borrowers they work with. For a broader overview of [construction financing in Ontario](/blog/construction-financing-ontario/), including bank vs private lenders, see our companion guide. It reflects the Construction Act amendments that took effect January 1, 2026, and covers both institutional and private construction lenders.
How a Construction Loan in Ontario Is Structured
A construction loan in Ontario is approved for a total commitment, then released in stages as work is completed and verified. The borrower pays interest only on what has been advanced, not on the full commitment.
Commitment amount vs what you can actually draw
The commitment letter sets the maximum. What you can draw at any moment is lower: it is the value of work completed to date, as verified by the lender's inspector or cost consultant, minus the holdback, minus any equity the lender expects you to have spent first. Brokers who explain this gap at the start avoid the most common "where is my money" call mid-build.
Loan-to-cost and loan-to-value on as-complete value
Lenders size construction loans two ways and use the lower answer:
- Loan-to-cost (LTC): the loan as a share of the total project budget, including land, hard costs, soft costs and interest.
- Loan-to-value (LTV): the loan as a share of the appraised "as-complete" value of the finished property.
Pricing and the percentages a lender will offer depend on lender type, mortgage position, location, the borrower's experience, the builder and the exit (sale or refinance). There is no single market number, so treat any figure you see as a lender-specific quote, not a rule.
Equity goes in first
Most construction lenders require the borrower's cash or land equity to be spent before the first loan advance. If the land is owned free and clear, its appraised value may count toward equity. If not, expect to show receipts for permits, design, servicing and early site work before Draw 1.
The Ontario Construction Draw Schedule, Stage by Stage
Every lender publishes its own draw schedule, and the commitment letter is the document that governs. There are two common formats.
Stage-based vs cost-based draws
Stage-based draws release a fixed percentage of the loan when a milestone is reached, such as foundation complete or roof on. This is common on single-family and custom home loans with banks and credit unions. Cost-based draws release funds against actual costs incurred, usually monthly, based on a cost consultant's report. This is standard on larger builds, multi-unit projects and most private construction loans. CMHC's Apartment Construction Loan Program, for example, funds through monthly construction draws once the loan agreement is executed.
Typical stages on a residential build
- Site work and foundation: excavation, footings, foundation walls, backfill.
- Framing and closed-in: framing, roof sheathing and shingles, windows and exterior doors installed.
- Rough-ins and insulation: plumbing, electrical and HVAC rough-ins inspected, insulation and drywall.
- Finishes: interior trim, flooring, cabinets, fixtures, exterior cladding.
- Substantial performance and occupancy: municipal occupancy permit or final inspection, followed later by holdback release.
Each stage normally needs a municipal building inspection sign-off before the lender will fund it. In the City of Toronto, required inspections are tied to the building permit, so the permit record is part of the draw file.
Cost-to-Complete: The Test Behind Every Draw
Cost-to-complete is the single most important number in a construction loan. Before every advance, the lender asks one question: after this draw, is there still enough money, from the undrawn loan plus any committed equity, to finish the project? If the answer is yes, the loan is "in balance" and the draw can proceed. If the answer is no, the loan is "out of balance" and the borrower must inject the shortfall before the lender funds anything else.
What the quantity surveyor or cost consultant does
On cost-based loans, the lender appoints a quantity surveyor (QS) or cost consultant, usually paid by the borrower. Their work comes in two parts. The initial cost review happens before the first draw. The consultant reviews the budget, construction contract, drawings, permits, schedule and insurance, and gives an opinion on whether the budget is realistic and complete. Missing line items, such as contingency, development charges or utility connections, are flagged here. Draw reports follow each month or stage. The consultant visits the site, measures the percentage complete for each budget line, reviews invoices and the contractor's progress claim, confirms holdback is being retained, and recalculates cost-to-complete. The lender funds based on that report, not on the contractor's invoice.
When the loan goes out of balance
Overruns usually come from three places: under-budgeted soft costs, change orders, and contingency used up early. When the consultant's revised budget exceeds the money available, the lender will hold the draw until the borrower deposits the difference. That is why a realistic contingency line and a clear change-order process matter as much as the loan amount.
Holdbacks Under Ontario's Construction Act (2026 Rules)
Holdback is the most misunderstood part of any construction draw schedule in Ontario, and the rules changed on January 1, 2026.
The 10% basic holdback and who holds it
Under the Construction Act, the owner must retain a basic holdback of 10% of the value of services and materials supplied under each contract and subcontract. The holdback protects subcontractors and suppliers who might otherwise lien the property. Construction lenders typically mirror this by advancing only 90% of verified costs, so the holdback money exists when it is time to release it. As Perley-Robertson, Hill and McDougall notes, the lender is usually involved in this process by deducting 10% from each advance.
Lien periods and substantial performance
Holdback is released once lien rights for that work have expired or been dealt with. A contractor or subcontractor generally has 60 days to preserve a lien, running from events such as substantial performance, completion, abandonment or termination, and must then perfect it within 90 days of the last day it could have been preserved (Nihang Law, 2026 homeowner guide). Those lien deadlines did not change in 2026. In practice, the final holdback draw is usually the last money a lender releases.
What changed on January 1, 2026
Amendments from Bill 216 and Bill 60 came into force January 1, 2026 (Ontario Bar Association; Fasken). The points that matter for a construction loan:
- Mandatory annual holdback release. On projects running more than a year, owners must publish a notice of annual release within 14 days after each contract anniversary, then pay the accrued holdback 60 to 74 days after the notice, unless a preserved or perfected lien blocks it. For contracts signed on or after January 1, 2026, this starts at the first anniversary. Contracts signed before then start on the second anniversary after that date.
- Owners can no longer give notice of non-payment of holdback. That option was removed.
- Proper invoices. An invoice is deemed proper unless the owner gives written notice of deficiencies within seven days of receiving it.
- Prompt payment still applies. The owner generally has 28 days from a proper invoice to pay, or must deliver a notice of non-payment within 14 days.
The practical effect for borrowers: on a longer build, holdback money may need to be released partway through, not only at the end. Ask the lender, before signing the commitment, how it will fund annual holdback release and how it aligns its draw cycle with the 28-day payment clock. The Act's deadlines run from the contractor's invoice, not from the date the lender funds.
Lien Searches, Lender Priority and Title Insurance
Why the lawyer searches title before every advance
Each advance is a mini-closing. Before releasing funds, the lender's solicitor runs a subsearch of title to confirm no construction liens, executions or other charges have been registered since the last advance, and confirms no written notice of lien has been received. The reason is priority. Under section 78 of the Construction Act, liens can take priority over a building mortgage to the extent of any deficiency in the holdbacks the owner was required to retain (Miller Thomson). Advances made after a lien is registered or notice is received can also lose priority. A lender that has not kept holdback in place, or that advances over a registered lien, puts its own security at risk. That is why a single lien registration, even a small one, can freeze a draw until it is vacated or bonded off.
Title insurance on construction loans
Many construction lenders require a lender's title insurance policy at the first advance. On construction files, ask whether the policy, or an endorsement, addresses construction lien risk and what conditions apply, since insurers may require holdback retention, a cost consultant or other controls. Title insurance supplements the subsearch process. It does not replace it.
The Interest Reserve
An interest reserve is a line in the budget, funded from the loan, that pays monthly interest during construction. It means the borrower is not making interest payments out of pocket while the property earns nothing. CMHC's rental construction program takes a similar approach, with interest during construction financed by the loan. The lender sizes the reserve by projecting the outstanding balance month by month along the draw schedule, then applying the loan rate. Because balances climb as the build progresses, most interest is paid in the final months. If the schedule slips by three or four months, the reserve can run dry, and the shortfall becomes a cost-to-complete problem. Build delay into the reserve, not just the contingency.
What Each Draw Needs: Document Checklist
Requirements vary by lender, but a complete draw request in Ontario usually includes:
- Draw request form signed by the borrower, showing the amount requested by budget line
- Contractor's progress claim or proper invoice, with holdback shown as retained
- QS or cost consultant draw report, or the lender's inspection report on stage-based loans
- Municipal inspection records for the completed stage
- Statutory declaration from the contractor confirming trades and suppliers have been paid to date
- Updated budget and schedule, including change orders and contingency used
- Builder's risk insurance confirmation, with the lender named as loss payee
- Clear subsearch from the lender's solicitor
- Holdback and lien status, including any published notices under the Construction Act
For new homes built for sale or under a builder contract, the lender will also confirm the builder is licensed with the Home Construction Regulatory Authority and that the home is enrolled with Tarion. Owner-builder and custom home rules differ and are covered in our guide to custom home construction loans in Ontario.
Worked Example: A Hypothetical Four-Draw Schedule
The numbers below are hypothetical and simplified to show the mechanics. They are not a quote from any lender. Suppose a borrower is building a detached home in Ontario with a total budget of $1,000,000: $960,000 of land, hard and soft costs, plus a $40,000 interest reserve. The lender commits $750,000 (75% loan-to-cost in this example), of which $710,000 is available for construction costs and $40,000 is the interest reserve. The borrower's $250,000 of equity is spent first. For simplicity, the 10% holdback is applied to all costs to date.
| Draw | Hypothetical milestone | QS cost to date | Less 10% holdback | Less borrower equity | Cumulative loan advanced | This advance |
|---|---|---|---|---|---|---|
| Equity | Permits, servicing, excavation | $250,000 | n/a | $250,000 | $0 | $0 |
| 1 | Foundation complete, framing started | $420,000 | $42,000 | $250,000 | $128,000 | $128,000 |
| 2 | Framed, roof on, windows in | $640,000 | $64,000 | $250,000 | $326,000 | $198,000 |
| 3 | Rough-ins, insulation, drywall | $830,000 | $83,000 | $250,000 | $497,000 | $171,000 |
| 4 | Substantial performance, occupancy | $960,000 | $96,000 | $250,000 | $614,000 | $117,000 |
| Holdback | Lien period expired, no liens | $960,000 | $0 | $250,000 | $710,000 | $96,000 |
The interest reserve is drawn separately each month, bringing the total advanced to $750,000.
The cost-to-complete check before Draw 3
Before Draw 3, the borrower and lender have paid $576,000 so far ($250,000 equity plus $326,000 in loan advances). On the original $960,000 budget, $384,000 is still needed to finish, and $384,000 of construction funds remain undrawn ($710,000 minus $326,000). The loan is in balance. Now suppose the consultant's Draw 3 report revises the budget to $1,010,000 after window and HVAC change orders. The project now needs $434,000 to finish, but only $384,000 is available. The loan is $50,000 out of balance, and the lender will hold Draw 3 until the borrower deposits $50,000 or the budget is reduced. A 5% to 10% contingency line in the original budget is what usually absorbs this kind of change.
Institutional vs Private Construction Lenders in Ontario
Both lender types fund construction in Ontario. The difference is structure and flexibility, not just price.
| Feature | Institutional (banks, credit unions, CMHC-backed programs) | Private lenders and MICs |
|---|---|---|
| Typical borrower | Strong credit and income, experienced builder, presales or a clear refinance | Equity-strong borrowers, tighter timelines, non-standard income or projects |
| Draw format | Often stage-based on homes, monthly cost-based on multi-unit | Usually cost-based with a lender-appointed inspector or QS |
| Approval and underwriting | Fuller income and covenant review, longer timelines | Focus on property, budget, builder and exit |
| Pricing drivers | Rate set off the lender's cost of funds and risk grade | Rate and lender fee set by LTV, position, term and risk |
| Holdback and lien controls | Strict, documented, solicitor-driven | Also solicitor-driven, practices vary by lender |
| Flexibility on overruns | Limited, equity injection expected | Sometimes a second mortgage or increase, at added cost |
| Exit | Converts to a term mortgage or CMHC take-out | Refinance to an institutional lender or sale |
Private construction loans in Ontario must be arranged through a mortgage brokerage, and since April 1, 2023 only agents with a Mortgage Agent Level 2 licence or brokers can deal in private mortgages, as set out by FSRA. Land and pre-development financing is covered in our land financing in Ontario guide; multiplex and garden suite financing have their own lender criteria.
Common Mistakes That Stall Construction Draws
- No contingency, or contingency spent on upgrades early. The first change order then puts the loan out of balance.
- Undersized interest reserve. Delays are normal; a reserve sized to a perfect schedule is not.
- Paying trades in full. If the owner does not retain the 10% holdback, the lender's priority is exposed and the lender may refuse to fund.
- Missing municipal inspections. No sign-off, no draw.
- Unpaid trades who register liens. A single registered lien can freeze the file until it is vacated.
- Ignoring the 2026 annual release rule on builds expected to run past one year.
- Change orders not sent to the cost consultant. Surprises at report time cost weeks.
- Builder's risk insurance lapsing or not naming the lender.
FAQ
How many draws does a construction loan in Ontario usually have?
Stage-based residential loans often run four to six draws plus a final holdback release. Cost-based loans on larger projects typically draw monthly. The commitment letter sets the schedule.
What is cost-to-complete on a construction loan?
It is the amount still needed to finish the project, recalculated before each draw. If undrawn loan funds plus committed equity do not cover it, the borrower must inject the difference before the lender advances.
Who pays for the quantity surveyor or cost consultant?
The borrower usually pays, even though the consultant is appointed by and reports to the lender. Expect a fee for the initial cost review and a fee for each draw report.
Does the lender hold back 10% of each draw?
Most construction lenders advance about 90% of verified costs so the owner's 10% Construction Act holdback is available when lien rights expire. That holdback is then released in a final draw, or annually on longer projects under the 2026 rules.
What changed in Ontario's Construction Act in 2026?
From January 1, 2026, annual release of holdback became mandatory on contracts running more than a year, owners can no longer give notice of non-payment of holdback, and invoices are deemed proper unless the owner objects in writing within seven days. Lien preservation and perfection periods did not change.
Why does the lender search title before every draw?
A registered lien or written notice of lien can affect the lender's priority for new advances under section 78 of the Construction Act. The subsearch confirms title is clear before money goes out.
Is a private construction loan in Ontario more flexible than a bank loan?
Private lenders often decide faster and focus more on the property, budget and exit than on income. They usually cost more, and they still require inspections, holdback retention and clear title before each advance.
Getting a Construction File Ready for Funding
Construction loans fund smoothly when the paperwork is ready before the first shovel. Have a detailed budget with a real contingency line, a signed construction contract, permits and drawings, proof of equity, builder licensing details where applicable, builder's risk insurance quotes, and a realistic schedule that includes room for delay. From there, talk to a licensed Ontario mortgage agent or broker who works with both institutional and private construction lenders, or review how brokers package construction files for private lenders. They can compare draw formats, cost consultant requirements and holdback practices across lenders, and match the file to the structure that fits the build and the exit.
Next steps: Borrowers · Speak With Our Team · FAQ
Richview Capital MIC is a licensed Mortgage Investment Corporation (Mortgage Administrator License #13171). This article is educational information for Ontario homeowners, not legal, financial, or tax advice. Rates, fees, LTV limits, and approvals vary by file and underwriting, and published ranges are subject to change and are not an offer of credit.